PROJECT NAME:
Marmaray CR1
TYPE OF SERVICE:
Design Verification
OTHER DETAILS:
Marmaray Project CR1 Phase Gebze- Haydarpaşa, Sirkeci –Halkalı Commuter Rail System Upgrading: Civil & Eletrical & Mechanical Systems Design Verification Service. Design Verification Service” for whole architectural design, mechanical systems design (heating, tunnel ventilation and station HVAC, firefighting and drainage) , electrical systems design ( Auxiliary Power supply, Sanitation-Tunnel Lightening, Small power- Earthing & Bonding, Fire Detection, Station Information, Management System (SIMS)), alignment and track work design, TBM tunnels and segmental lining design, 32 stations, track way structures (tunnels, bridges, underpasses), substations, depots and stabling yards (including workshops) for the construction of Commuter Rail and Intercity Train Facilities in the scope of Marmaray Project –CR1 Phase. The total length of the system for the CR 1 phase is 43+13 =56 km.